At a Crossroads for India’s BESS Market: How a 100 GWh Tender Pipeline Can Bridge the Execution Gap
Analyze India's battery energy storage landscape. Learn how a 100 GWh pipeline, VGF policies, and new revenue models are reshaping the BESS execution roadmap.
Author:

Introduction: A Critical Turning Point for a Multi-Gigawatt-Hour Market
As global installed battery energy storage capacity is set to surpass 108 GW by 2025—a year-on-year increase of approximately 40%—India occupies a unique position: it is neither a mature market nor merely an experimental one. According to Vaibhav Singh, Head of Strategy at Tata Power, India’s energy storage sector stands at a crossroads: on one side lies a procurement pipeline exceeding 100 GWh, while on the other, only about 10.3 GW of capacity is currently operational. This significant gap represents both the industry’s greatest opportunity and its most daunting execution challenge.
Over the past three years, India’s energy storage policy has focused on rapidly stimulating demand. Through mechanisms such as Viability Gap Funding (VGF), energy storage obligations, and supportive transmission policies, the sector has transitioned from conceptual discussions to grid-scale deployment. Now, the industry must address a more pragmatic question: can the projects that have already been awarded truly be transformed into high-quality assets—assets that are bankable, operational, and suitable as collateral?
Drawing on an in-depth interview with Vaibhav Singh, Head of Strategy at Tata Power, and incorporating public data from organizations including the Central Electricity Authority (CEA), IEEFA, Wood Mackenzie, and JMK Research, this article provides a systematic breakdown of the key obstacles and potential solutions for India’s Battery Energy Storage System (BESS) market—covering six critical dimensions: execution bottlenecks, revenue models, safety governance, supply chain localization, technology pathways, and the role of policy.
I. Market Coordinates: India’s Position in the Global Energy Storage Landscape
To understand the unique nature of India’s energy storage market, one must first situate it within the global context. In 2025, global new installations of battery energy storage are projected to reach approximately 108 GW, with China accounting for about 60% of this total. By comparison, India’s operational base remains relatively small—as of June 2026, the country had approximately 10.3 GW of energy storage capacity in operation, of which battery energy storage systems (BESS) accounted for about 2.9 GW/8.3 GWh.
However, India’s distinctiveness lies not in its current scale, but in the drivers of its demand. Unlike markets in Europe or Australia, where demand is largely fueled by arbitrage opportunities, India’s need for energy storage stems from structural shifts within its power system: rising solar photovoltaic (PV) penetration, the challenge of managing peak demand during evening hours, policy mandates for Firm and Dispatchable Renewable Energy (FDRE), the gradual development of ancillary services markets, and the need to alleviate congestion on the transmission network. In short, the question is no longer whether India needs energy storage, but rather how quickly the entire ecosystem can build out this capacity and bring it online.
This structural demand also offers a "late-mover advantage": India does not need to develop its entire industrial value chain from scratch; instead, it can leverage cost-reduction pathways and technical solutions already proven in China, Europe, and the United States. Government policy instruments—such as Viability Gap Funding (VGF) subsidies, mandatory energy storage quotas, and procurement mechanisms linked to transmission projects—collectively provide a multi-pillared support structure for demand.
"The primary risk is that the pace of procurement growth is outstripping the maturation of the industrial ecosystem and financial markets." — Vaibhav Singh, Head of Strategy, Tata Power
II. The Core Contradiction: The Disparity in Scale Between Tendered and Operational Capacity
A telling comparison highlights the issue: as of June 2026, the cumulative capacity of energy storage systems (ESS) tendered in India has surpassed 100 GWh, yet only about 8.3 GWh of battery energy storage systems (BESS) are actually connected to the grid and operational. In other words, for every 10 watt-hours tendered, less than one is currently contributing to the grid.
An analysis by the IEEFA following the 2025 auctions for standalone BESS further exposes the deeper risks underlying this gap. That year, India awarded 10.4 GWh of standalone BESS capacity; however, nearly three-quarters of these projects—configured for a two-hour duration—were assessed as facing potential viability crises given their winning bid prices. NTPC has even cancelled some of the capacity that had already been awarded, signaling that this "execution gap" is no longer merely a theoretical concern, but an unfolding reality.
Consequently, the focus of competition in India’s energy storage sector is shifting: the priority is no longer about securing the largest volume of tenders, but rather about successfully constructing and operating the awarded projects to ensure long-term asset returns. As Singh has repeatedly emphasized, the core challenge for the next phase lies not in announcing ever-larger gigawatt-scale figures, but in transforming a massive procurement pipeline into a portfolio of assets that are bankable, technically robust, and operationally viable.

III. Execution Bottlenecks: Four Hurdles from Bid Award to Commercial Operation
3.1 Bankability Risks: When Tariff Declines Outpace Cost Reductions
Competitive auctions have successfully driven down tariffs for Battery Energy Storage Systems (BESS) in India—between 2022 and 2026, winning bids for 2-hour and 4-hour standalone BESS projects fell by over 80%. However, the cost of battery packs themselves declined by only about 40% during the same period. Because tariffs dropped faster than costs, the resulting gap has become the single greatest threat to project bankability.
By 2025, the lowest tariff for a 2-hour standalone BESS project had fallen to approximately 148,000 INR/MW/month, whereas the industry-accepted benchmark for viability is roughly 230,000 INR/MW/month—a gap of nearly 60%. Approximately 75% of the awarded 2-hour capacity falls within this high-risk zone.
A deeper issue is the lack of technical qualification thresholds in Indian auctions. Nearly half of the awarded capacity has been allocated to market participants with no prior experience in executing standalone BESS projects. Having secured contracts at overly aggressive tariff levels, these developers often face a cascade of subsequent issues, including construction delays, the need to renegotiate technical specifications, financing difficulties, or returns that fall short of expectations.
3.2 Hidden Bottlenecks in the Project Development Lifecycle
While energy storage projects may appear simpler than power generation projects—requiring less land and shorter construction timelines—their actual implementation is complex. BESS projects still necessitate land approvals, grid interconnection, power evacuation infrastructure, various statutory permits, bankable Power Purchase Agreements (PPAs), equipment procurement, and final commissioning and grid synchronization. A bottleneck at any stage can delay a project’s Commercial Operation Date (COD).
For financiers, battery technology introduces uncertainties rarely seen in traditional power generation projects—such as battery degradation rates, the costs and timing of capacity augmentation, cycle life limitations, availability guarantees, and the residual value of the batteries. Each of these factors must be accurately priced into financial models. The market is shifting from policy-driven procurement toward bankable execution. Factors such as supply chain readiness and full-lifecycle economics are gaining weight—now rivaling, or even surpassing, the importance of the bid price itself.
3.3 Supply Chain and Exchange Rate Exposure Over 12–15 Year Contract Terms
India remains heavily dependent on imported battery cells. With energy storage procurement contracts typically spanning 12 to 15 years, developers face long-term exposure to battery price volatility, exchange rate fluctuations, the fulfillment of supplier warranties, and ongoing maintenance costs.
If a bidder submits a highly competitive price based on the expectation that battery costs will continue to fall, but the actual rate of cost reduction falls short, the project’s underlying economics will erode. Consequently, Singh argues that a mature auction mechanism should not simply select the lowest bidder; rather, it should evaluate a credible combination of price, technical solutions, financing capacity, and delivery experience.
3.4 Policy Improvements Are Underway, with Further Scope for Progress
It is encouraging that policy adjustments are moving in the right direction. For projects supported by Viability Gap Funding (VGF), the commissioning period has been shortened to 18 months, contract terms have been extended to 12–15 years, and 70% of the VGF funds can now be disbursed prior to the Commercial Operation Date (COD). These changes directly improve developer cash flow and project bankability.
Future improvements could include: standardizing tender documentation; establishing mechanisms for in-depth communication both before and after bid awards; strengthening payment security arrangements; setting practical pre-qualification thresholds; defining clear risk-sharing rules for changes in law and import tariffs; and implementing more rigorous monitoring of project milestones. The collective goal of these measures is to narrow the gap—in terms of both time and risk—between the awarding of a tender and the project’s Commercial Operation Date (COD).
IV. Evolution of Revenue Models: From Fixed Rates to Market-Based Operations
The historical mission of India’s first generation of Battery Energy Storage System (BESS) projects was to demonstrate to the grid that battery storage technology could be integrated reliably. For the subsequent second generation, the core objective has shifted: how to maximize the value derived from every megawatt-hour and every battery cycle.
Currently, most operational assets remain anchored to contractual capacity payments or storage leasing fees—a model that provides financiers with predictable cash flows. However, as the market matures, the economic value of batteries is extending into a broader range of applications: peak shaving during evening hours, daytime solar arbitrage, smoothing the output of renewable energy, ancillary services, and—as regulatory frameworks evolve—various grid-support services.
A particularly notable trend is the rise of merchant-based BESS. India is transitioning from a market driven almost exclusively by long-term contracts toward a more diversified revenue structure—one that combines contracts, merchant participation, and hybrid models. Today, nearly half of India’s installed BESS capacity carries some exposure to merchant revenue, with companies such as Adani, ACME Solar, and Juniper Green already having successfully commissioned projects. The significance of the merchant model lies in its ability to elevate the value of energy storage: moving beyond the mere collection of fixed capacity payments toward the active monetization of flexibility within the market.

V. Upgrading Asset Management: The Value Trade-off in Every Battery Cycle
The logic behind managing Battery Energy Storage System (BESS) assets differs fundamentally from that of traditional solar or wind assets. While the primary objective for solar and wind assets is to maximize power generation and availability, BESS asset managers must simultaneously optimize a complex set of variables: State of Charge (SoC), Depth of Discharge (DoD), cycle frequency, battery degradation rates, capacity augmentation schedules, charge/discharge efficiency, and prevailing market prices.
A critical concept here is the opportunity cost of a battery cycle. Discharging during a given cycle might yield a certain profit now, but waiting a few hours—when the price spread is wider—could generate even greater returns. Conversely, excessive cycling accelerates battery degradation, shortening the asset's effective lifespan. Consequently, BESS asset management has evolved into an interdisciplinary field, blending engineering expertise with trading strategies and optimization algorithms.
Another notable shift concerns the evolution of energy storage duration. While 2-hour systems were once the undisputed market standard, demand for 4-hour systems has risen significantly since the second half of 2025—a trend also observed by JMK Research. As operational fleets expand and asset owners accumulate years of data on degradation and dispatch, a specialized BESS operational ecosystem is set to emerge, centered on Energy Management Systems (EMS), power forecasting, algorithmic dispatch, battery health analysis, and portfolio optimization.
Core operational metrics will also shift. In the past, the primary question was simply whether the battery was functional; in the future, the focus will be: while maintaining long-term battery health, have we maximized the risk-adjusted value of every single cycle?
VI. Safety Governance: Why Unit-Level Compliance Does Not Equate to Site-Level Safety
As GWh-scale battery energy storage systems (BESS) are deployed across India, safety has evolved from a mere technical detail into a systemic issue that determines the industry’s public acceptance. Singh’s core argument is that safety is not just a certification step to be completed after a project is built; rather, it is an overarching engineering philosophy that spans everything from individual battery cells to on-site emergency response.
A robust safety framework begins with high-quality cells and modules, supported by reliable battery management systems (BMS), thermal management designs, electrical protection, gas and smoke detection, fire compartmentalization, and engineering measures to prevent the propagation of thermal runaway. India’s regulatory framework is also tightening, with new safety requirements scheduled to take effect in April 2027.
A common misconception is that if battery cells meet safety standards, the entire energy storage station is inherently safe. In reality, this is far from the case. Developers must evaluate safety across five distinct levels: cells, modules, racks, containers, and the site as a whole. Current reference frameworks include international standards such as IEC 62619, the IEC 62933 series, and UL 9540A (for thermal runaway testing), alongside India’s own BIS standards.
Thermal runaway must be treated as a credible failure mode rather than a low-probability, negligible event. The design objective should be to ensure early detection, isolate affected equipment, prevent the spread of fire, and protect first responders on-site.
Community engagement is equally critical. Simply informing local residents that a facility complies with national standards is insufficient. Developers, EPC contractors, and system integrators must explain to the surrounding community what the facility contains, what preventive systems are in place, how fires or other emergencies are managed, and whom residents should contact if issues arise. Local fire departments and disaster management agencies should be familiar with the facility well before commissioning—not just arriving for the first time after an incident has occurred.
As BESS technology expands into commercial and industrial (C&I) applications and residential settings, the proliferation of distributed, kilowatt-hour-scale systems will bring safety concerns closer to the daily lives of the general public. A single safety incident resulting from poor management could undermine public trust in the entire industry. Installers therefore have a strong incentive to go beyond minimum compliance standards by establishing transparent safety governance, independent inspections, and incident reporting mechanisms.
VII. Supply Chain Localization: A Phased, Realistic Path
When discussing the localization of energy storage in India, it is essential to distinguish between two levels: the localization of Battery Energy Storage Systems (BESS) and the localization of the entire battery value chain. These two objectives entail vastly different levels of difficulty and timeframes.
Localizing components such as containers, steel structures, transformers, switchgear, cables, Power Conversion System (PCS) parts, battery pack assembly, system integration, and software can be achieved within a relatively short period. The true challenge lies upstream—in the production of cathode and anode active materials, electrolytes, and separators, as well as the sourcing of critical minerals further up the supply chain. Success in these areas requires economies of scale, accumulated technical expertise, intellectual property, specialized equipment, and a stable supply of raw mineral materials.
The Indian government’s Production Linked Incentive (PLI) scheme for Advanced Chemistry Cell (ACC) battery storage—with a budget of 181 billion Indian rupees (approximately $1.9 billion)—targets a manufacturing capacity of 50 GWh. However, while 40 GWh of capacity has been allocated, only 1 GWh of PLI-supported capacity is currently operational. The Indian government itself acknowledges that domestic demand is currently met primarily through imports.
Estimates from Wood Mackenzie offer a more nuanced perspective: although India plans to develop over 226 GWh of battery manufacturing capacity by 2035, gaps in scale, financing, and the broader industrial ecosystem mean that the initial cost of domestically produced batteries could be 25% to 40% higher than that of imported alternatives. This suggests that localization policies should focus on fostering long-term competitiveness, rather than pursuing localization for its own sake.
Within this decade, significant localization of battery pack assembly, Battery/Energy Management Systems (BMS/EMS), system integration, and Balance of System (BoS) equipment is entirely feasible. As planned "gigafactories" come online, domestic cell production capacity will expand; however, achieving full self-sufficiency in upstream materials will take considerably longer. The ACC PLI scheme’s requirement to increase domestic value addition from 25% to 60% over five years represents a pragmatic starting point.
VIII. Technology Mix: A Parallel Approach to Short-Duration and Long-Duration Energy Storage
India does not need to choose between short-duration and long-duration energy storage (LDES); both serve distinct needs within the power system.
Lithium-ion battery energy storage systems (BESS) with a duration of 2 to 4 hours are best suited for shifting daytime solar generation to meet evening peak demand, as well as providing rapid-response grid ancillary services. Conversely, when requirements extend to balancing power throughout the night, addressing multi-day shortfalls in renewable energy generation, or even managing seasonal system flexibility, the value of pumped-storage hydropower (PSH) and other LDES technologies becomes clear.
The planning data from the Central Electricity Authority (CEA) reflects this combined approach. Total national energy storage demand is projected to grow from approximately 82 GWh in the 2026–27 fiscal year to 411 GWh by 2031–32—comprising roughly 175 GWh from pumped-storage hydropower and 236 GWh from BESS.
The configuration of the tender market is also evolving. While the standalone BESS market in 2025 remains dominated by 2-hour, two-cycle-per-day configurations, there has been a notable increase in interest regarding 4-hour systems during the second half of the year.
Beyond lithium-ion batteries and pumped-storage hydropower, there is also a role for flow batteries, sodium-ion batteries, thermal energy storage, compressed-air energy storage, and—for ultra-long-duration applications—hydrogen-based storage. The policy approach advocated by Singh emphasizes technology neutrality and service-oriented procurement. Rather than mandating specific battery chemistries, procurers should define performance requirements—such as discharge duration, response time, availability, cycle life, and total energy delivery—allowing various technologies to compete within the applications where they are most effective.
IX. The Role of Policy: From Subsidy-Driven to Market-Framework Building
At the current stage, the primary role of the Indian federal government is to create markets and mitigate risks. Energy storage generates value for the entire power system—value that is difficult to fully internalize through the revenue streams of individual projects alone. This is why policy instruments such as Viability Gap Funding (VGF), energy storage obligations, competitive procurement guidelines, and manufacturing incentives are essential; they bridge the gap between the systemic economic value of energy storage and the bankability of specific projects.
The scale of public support is substantial. Under the June 2025 Power System Development Fund (PSDF) initiative, 54 billion rupees in VGF has been allocated for 30 GWh of Battery Energy Storage Systems (BESS)—equating to approximately 1.8 million rupees per MWh—with 25 GWh distributed across 15 states and 5 GWh undertaken by NTPC. Including other VGF components, the Central Electricity Authority (CEA) estimates the total supported capacity at approximately 43.85 GWh. Similarly, the Production Linked Incentive (PLI) scheme for Advanced Chemistry Cells (ACC)—backed by 181 billion rupees—represents an extension of this same logic to the manufacturing sector.
However, the ultimate policy objective should not be for energy storage to remain permanently dependent on subsidies. A logical evolutionary path would be: a transition from government-supported early-stage deployment to contract-driven private investment, followed by a hybrid model combining contracts and merchant-market participation, and finally, a stage where private capital assumes the primary market risks.
To complete this transition, investors require several key conditions: predictable electricity market rules, well-functioning ancillary services markets, price signals that accurately reflect the true value of flexibility, and creditworthy off-takers. Furthermore, financiers need a sufficiently long track record of operational data to make confident assessments regarding battery degradation, residual value, and capacity augmentation.
X. Conclusion: The Real Test for the Next Five Years
In summary, the obstacles currently facing India’s energy storage market can be categorized into five dimensions: bankability, execution capability, market design, supply chain depth, and operational expertise.
India has already demonstrated its ability to generate significant market interest through auctions. The real test, however, is twofold: can the winning bid prices support sustainable projects? And of the more than 100 GWh in the current tender pipeline, how much will actually transition into operational assets over the coming years?
The solution is not to slow down procurement, but rather to ensure more reliable project delivery through better-calibrated qualification thresholds, timely grid interconnection, standardized contractual terms, clear accountability for project milestones, and procurement timelines that align with the practical realities of equipment lead times and financing cycles. Furthermore, the market must move beyond the narrow view of energy storage as a provider of a single service, fully recognizing its multifaceted value—including energy shifting, rapid response, reserve capacity, congestion management, and capacity availability.
Encouragingly, most of these challenges are merely "growing pains" typical of an emerging infrastructure asset class, rather than signs of insufficient demand. Over the next five years, the narrative for India’s energy storage sector will shift from "whether to build" to "how to build and operate at scale—safely, competitively, and profitably." The outcome of this test will determine whether India can truly establish itself as a major pillar in the global energy storage landscape.
Data and Sources
The core facts and figures in this article are drawn from the following public sources: insights from Vaibhav Singh, Head of Strategy at Tata Power; data from the Central Electricity Authority (CEA) of India’s National Electricity Plan; IEEFA’s feasibility analysis on standalone BESS auctions for 2025; Wood Mackenzie’s research on India’s battery supply chain; JMK Research’s BESS market tracker; announcements regarding the Ministry of Heavy Industries’ ACC PLI (Production Linked Incentive) scheme; new safety regulations for energy storage—published in the *Gazette of India* and set to take effect in April 2027; and project announcements from NTPC. All data presented is current as of June 2026; figures labeled as "projected" or "planned" represent institutional forecasts and do not reflect realized outcomes.